Tools needed for installation
Level
Cement mixing tub
Shovel
Trowel
Hole coring machine with 4” bit
Access to water hose
Materials to build brace (see “Install Tip” at bottom of page)
Installing into Existing Sidewalk
Core holes no less than 4” diameter and no less than 11” deep into sidewalk. Fill holes with Super Por-Rok or epoxy grout. Place Excalibur Rack into holes, making sure the rack is level. The welds at the base should be just bellow the surface. Make sure the rack is level and held in place until the grout has set.
Installing into New Sidewalk
Stake Method:
- Use rack to measure exact location in pour bed.
- Pound stake into pour bed where end of rack will sit. Slide rack end onto stake. You may need to dig the end of the rack into the sand to make sure the rack sits at least 35” above final grade level. The stake keeps the rack straight while the concrete is being poured.
- Make sure the rack is level and true. Pour concrete around the rack. Make sure the rack is not touched until the concrete has completely set.
Sleeve Method:
- Place corrosion resistant sleeve (min. 3” ins ide diameter) in sand pour bed in exact location where rack will be installed. Make sure top of sleeve is at same level as desired finished concrete surface. Fill sleeve with sand to keep it in place and prevent it from filling with concrete.
- Pour concrete and allow to cure.
- After appropriate cure time, dig out sand from sleeves and insert racks, making sure they are level and at the appropriate height. Pour in Super Por-Rok or epoxy grout and allow to set.