Tools Needed for Installation
9/16” Wrench/Socket
3/4” Wrench/Socket
1/4” Drill Bit or 3/8” Masonry Drill Bit (depending on anchor type)
Tape Measure
Drill (Hammer Drill Recommended)
Hammer
Level
Saw for cutting track
Installation:
Before installing: Make sure the wall is strong enough to accommodate the rack fully loaded with bikes. Compare parts shipped with rack to parts list. Call Dero if any parts are missing.
- Mount 24” Slotted Tracks vertically to the wall with the appropriate anchors. Use a level for greatest accuracy. The bottom edge of the Slotted Track should be approximately 72” off the floor. The Slotted Tracks should be 4’ apart from each other, and the end Slotted Tracks should be 2’ from the eventual position of the end of the Trolley track.
- Mount the remaining 24” Slotted Tracks horizontally and protruding from the wall so that the slotted surface of the Slotted Track is 4.25” below the top edge of the vertical 24” Slotted Track. Use the Knee Braces, Angle Brackets, and the Spring-loaded Nuts and Hex Head Cap Screws to secure the horizontal Slotted Track in place.
- Make sure the horizontal Slotted Track is level. Adjust if necessary.
- Attach the Track Rack to the Wall Mount assemblies by securing the Channel Trolley Supports to the horizontal 24” Slotted Track with the remaining Spring-loaded Nut and Hex Head Cap Screw. The edge of the Slotted Track Mounting Bracket should be flush with the edge of the 24” Slotted Track.
- Follow the installation instructions for the basic Track Rack unit (ceiling mount) to complete the assembly.